Assemble the required information
The responsible party gathers project-specific selections, manufacturer information, drawings, calculations, certifications, samples, or reports specified for the item.
A strong process begins by translating the contract documents into a complete, understandable register that the project team can plan around.
Review Division 01 and technical sections; capture specific deliverables with source references.
Assign responsibility and calculate need dates from procurement, fabrication, and installation milestones.
The responsible trade assembles the required information and the contractor checks completeness and coordination.
The design team reviews for conformance with the design intent; comments and status are returned.
Resubmit when required, maintain the approved record, and track closeout deliverables.
SubmittalsHQ focuses on the front of this process: specification processing, register creation, and review of the extracted requirements. It is not presented as a downstream routing or approval platform.
The process begins with the contract documents, not with a blank tracking log. Review Division 01 for administrative rules and technical sections for specific deliverables. Complete the list with requirements found in drawings, addenda, owner standards, scope exhibits, and other applicable documents.
Each requirement should retain enough source information for a second person to check it without repeating the entire search.
After content review, assign preparation responsibility and establish a packaging strategy. Then work backward from construction milestones to create required-submit dates. Early-release materials, long fabrication durations, samples, mockups, delegated design, and testing often deserve special sequencing.
The responsible party gathers project-specific selections, manufacturer information, drawings, calculations, certifications, samples, or reports specified for the item.
Dimensions, openings, power, controls, finishes, structural support, adjacent work, and related trades should be coordinated before design review.
The contractor verifies completeness, marks selections and deviations, confirms field conditions where required, and applies the required review indication.
Terminology varies by project: approved, approved as noted, revise and resubmit, rejected, reviewed, or no exceptions taken are common examples. The contract documents define what each status permits. Teams should not assume that similar words have identical consequences across projects.
A status stamp is not the entire review. Comments may require incorporation into fabrication or installation, coordination with another package, or a formal resubmittal. Distribute the response to the people responsible for acting on it.
When resubmission is required, identify changes, respond to prior comments, and avoid introducing unmarked revisions. The register or downstream platform should preserve package versions and the current disposition.
Approved information should remain available to procurement, fabrication, field supervision, quality control, and closeout teams. A completed workflow connects the reviewed package to the work rather than treating approval as the end of an administrative task.
A strong register makes requirements visible, assigns ownership, exposes schedule dependencies, and provides a place to reconcile the planned list with actual packages. It does not perform the work, but it gives the team a common control point.
The earlier that control begins, the more opportunity the team has to address missing information before it affects fabrication or installation.
The responsible design professional reviews submittals as defined by the contract. The contractor generally performs its own review first. Specific approval authority and terminology are governed by the project documents.
Use the duration stated in the contract documents and account for contractor preparation, coordination, delivery, design review, possible consultant review, resubmission, procurement, and fabrication.
Generally, approval does not automatically authorize an unmarked deviation or change contractual requirements. The project’s contract and change procedures control.
It helps process specifications and build and review the initial register. Downstream package preparation, routing, design review, responses, and version control remain in the project’s established workflow.
Assume switchgear is required on site October 1. The supplier confirms 24 weeks for fabrication after approved drawings and four weeks to prepare the initial shop drawing. The project allows 10 business days for design review, and the team wants one review cycle of contingency.
The project team should not simply assign the shop drawing a convenient due date. Begin with delivery, subtract fabrication, then allow time to release the order after approval. Add the initial review period, contingency for comments and resubmission, contractor coordination, and supplier preparation. Also confirm whether approved drawings, final electrical characteristics, utility coordination, or protective-device studies are prerequisites to fabrication.
This calculation may show that the package is an immediate priority and that design inputs are needed even earlier than the first formal submittal. The register makes that dependency visible; the project schedule and procurement plan determine the actual dates.
Product data, shop drawings, and calculations may be transmitted together when they support one coordinated review. Preserve the individual requirements in the register, then associate them with the package used by the downstream platform. This prevents packaging decisions from erasing the original obligations.
Large systems may require phased releases, separate suppliers, early selections, or discipline-specific review. Split the planned packages while retaining the source requirement that connects them. Document the decision so the team can reconcile packages with the contract requirement.